This component will support the development of three major transport corridors by widening and strengthening o f about 461 km State Highways (SH). The road corridors and links were identified through the Strategic Options Study, which determined their priority among all the state highways, and were subjected to economic analysis to establish their economic viability.
The three corridors serve 10 districts, improve transport connectivity to current and planned industrial and mining areas and tourist locations, connect major National Highways and ports in Odisha and neighboring Andhra Pradesh, and enhance the availability of transport services to poor and tribal communities living along the comdors.
The current roads are mostly of single lane standard (3.5 meter), with some intermediate lane (5.5 meter) sections, and will be widened to double-lane (7 meters), and will have 2.5 meter shoulders on each side for a total road width o f 12 meters, except in some environmentally sensitive areas and heavily built up locations, which will be designed and developed to minimize environment and social impacts.
The list o f roads to be taken up under the project is listed in Table 1 below. In addition, the project will finance the cost o f repairing a high-level bridge on the Bansadhara River, which was damaged during the August 2007 floods. The bridge (150 meter span) is located on one o f the project corridors (Berhampur-Bangi Jn-Rayagada ) and will be reconstructed along with works for river training, embankment and approach roads.
Corridor Name | KM | Road Link | SH | KM | Districts Covered | |
Jagatpur-Kendrapara-Chandbali- Bhadrak- AnandPur |
201 |
Jagatpur-Kendrapara-Chandbali |
SH-9A |
99 | Cuttack,Kendrapara & Bhadrak |
|
Chandbali-Bhadrak | SH-9 | 53 | Bhadrak | |||
Bhadrak-AnandaPur | SH-53 | 49 | Bhadrak-Keonjhar | |||
Khariar-Bhawanipatna | Khariar-Bhawanipatna | SH-16 | 68 | Kalahandi,Bolangir & Nuapada | ||
Berhampur-Bangi Jn-Jk Pur(Rayagada) Including reConstruction of flood damaged bridge(150 m) over Bansadhara river | 192 | Berhampur-Banki Jn | SH-17 | 150 | Ganjam,GajaPati,Rayagada | |
Banki Jn-JK Pur(Rayagada) | SH4 | 42 | Rayagada | |||
Total | 461 | 461 |
In this component the Government will borrow directly from the World Bank for the cost of the Project. The list of the road packages identified by the Government for improvement are as follows.
Bhwanipatna to Khariar is of length 68 kms and is located in Kalahandi,Nuapada and Bolangir districts of Odisha. It starts from Km 2/0( near Bhawanipatna) and ends at Km 70/0(near Khariar) . The sub-project is a section of SH-16 and is an important route connecting to NH-201 and NH-217. The existing road carriageway is of single/intermediate lane, with the road badly damaged on some portions like bridge approaches 8/600,10/537,20/979,27/650,27/949,28/928,29/239 due to overtopping of flood water of Tel River in last monsoon. The bridges at locations 54/791 and 58/760 are under re-alignment. The road traverses mostly through plain and rolling terrain and have mostly flat gradient and good geometry.
Bhadrak to Chandabali (Km 0/0 to Km 45/0 of SH-9) and Bhadrak to Anandapur (Km 0/0 to Km 50/0 of SH-53) are located in Bhadrak and Keonjhar districts. The road stretch Bhadrak.-Chandabali starts at Bhadrak (0/0) and ends at Chandabali (45/0). Bhadrak-Anandapur stretch starts form Kolkata-Chennai 4-lane highway (NH-5) at chainage 155/0.The Chandbali-Bhdrak-Anandapur stretch traverses through plain terrain and has mostly flat gradients with good geometry. The existing road carriageway is of single/intermediate lane,with the road badly damaged in many locations especially at Nalagandha,Ghusura causeway portion (Km 36/005) in Bhadrak-Chandbali stretch.
Berhampur to Taptapani road (Km 0/0 to Km 41/0 of SH-17) is of length 41 kms and is located in Ganjam district. This stretch of road takes off form NH-217 at 18th Km near Berhampur. The road traverses mostly through plains and has mostly flat gradients with good geometry.The existing carriageway width (7m is of single/intermediate lane. Major re-alignment of the road section is proposed at Km 6/800 (R/S) to avoid sharp consecutive horizontal curves. There are total 10 no.s of existing bridges, one of this is major and remaining 9 are minor bridges. Out of 9 minor bridges two at Km 11/270 and 29/500 are to be reconstructed and the remaining seven are to be rehabilitated. Berhampur to Taptapani section caters the needs of nearest town Digapahandi and it is also an important road junction.
Agency | M/s Patel– ARSS JV Plot No. 38, Sector – A, Zone - D Mancheswar Industrial Estate, Bhubaneswar – 751 010 |
Estimated Cost | Rs. 103,43,94,251 |
Contract Amount | Rs.105,51,39,120 |
Date of Commencement | 20.02.2009 |
Date of Completion due | 19.08.2011 |
Length Handed over to the Contractor | |
For Immediate Execution | 5 km on November, 2009 |
5 km on November, 2009 | 28 km on April 19, 2010 [ Km 35 – Km.63 ] |
Length Handed over to the Contractor : | 5 km on November, 2009 |
For Immediate Execution | [ Km. 5/0 to Km. 6/500, Km. 14/0 to Km. 17/5 ] |
MILE STONES as per Contract. : | |
1st Milestone - Km.18/0 to Km. 46/0 of SH-16 : | 10 Months from the date of commencement of works i.e. till 19th Dec, 2009 |
2nd Milestone - Km.46/0 to Km.70/0 of SH-16 : | 20 Months from the date of commencement of works i.e. till 19th Oct, 2010 |
Completion of the whole work : | 30 Months from the date of commencement of works i.e. till 19th Aug, 2011 |
Revised Mile Stones proposed as per EOT | |
1st Milestone Km.35/0 - 63/0 : | 28 Kms |
2nd Milestone Km. 63/0 – 70/0 and 18/0 - 35/0 : | 24 Kms |
Completion of the whole work : | 16.0 Km |
TOTAL | 68.0 Km |
One independent Executive Engineer of OWD has been designated as “Resident Engineer” for this package to administer the Contract as “Engineer”. Theme Engineering Services Private Limited was hired for assisting the Engineer in Construction Supervision. This interim arrangement shall continue till a regular Supervision Consultant is hired through Bank Procurement process.
[ Theme Engineering Services Pvt. Ltd., Jaipur ]
Theme Engineering Services Pvt. Ltd. has commenced its services with effect from 1st Nov, 2010. The Expenditure for this interim arrangement shall be borne by the Government of Odisha.
Items | Provisions |
Upto-Mar, 2011 |
Upto April,2011 |
Financial Progress (Rs. Cr.) |
105.51 |
13.37 |
15.38 |
Physical Progress | |||
Road |
68 km |
BC:2.0 km |
BC:2.0 km |
Tree Cutting (No.): |
2301 |
917 |
917 |
Land Acquisition (villages) |
41 |
40 |
40 |
R&R (PAPs) |
4.4km |
PAPs Asper RAP – 97 Nos (1st MS) |
PAPs Asper RAP – 97 Nos (1st MS) |
Utility Shifting : |
|
|
|
Pipeline shifting |
10050mtr |
4000 mtr completed |
4000 mtr complted |
Tube Wells |
52nos |
27 no.s |
27 no.s |
Electric Lines |
68 km |
55 kmcompleted |
55 km completed |
Bottleneck :
Agency : | M/s SOMDATT Builders– ARSS JV Plot No. 38, Sector – A, Zone - D Mancheswar Industrial Estate, Bhubaneswar – 751 010 |
Estimated Cost : | Rs. 194,31,12,992 |
Contract Amount : | Rs.216,23,17,622 |
Date of Commencement : | 02.08.2011 |
Length Handed over to the Contractor : For Immediate Execution |
17 km on November, 2009 |
1st Mile Stone : | Rs. 194,31,12,992 |
Length Handed over to the Contractor : For Immediate Execution |
5 km on November, 2009[ Km. 5/0 to Km. 6/500, Km. 14/0 to Km. 17/5 ] |
MILE STONES as per Contract. | |
1st Milestone – |
10 Months from the date of commencement of works, i. e. till 2nd Dec 2009 i.e. till 21st July, 2009 |
2nd Milestone – |
20 Months from the date of commencement of works i.e. till 2nd Oct, 2010 |
Completion of the whole work | 30 Months from the date of commencement of works i.e. till 2nd Aug, 2011 |
Revised Mile Stones proposed as per EOT | |
1st Milestone |
34.7 Kms |
2nd Milestone SH – 9 : Km. 30/0 – 45/0 SH – 53: Km. 0/0 - 12/0, 26/0 – 32/0 : [ Less built-up area 4. 5 kms ] |
28.5 Kms |
Completion of the whole work SH – 9 : Km. 0/0 – 2/0 SH – 53: Km. 39/0 – 42/3 including builtup areas leftout : Addl. : Km. 42/3 to NH-215 Jn. (1.8 Kms). Dropped: Km. 42/3 – 50/0 of SH – 53 |
25.90 Km |
TOTAL : | 89.1 Km. |
One independent Executive Engineer of OWD has been designated as “Resident Engineer” for this package to administer the Contract as “Engineer”. Theme Engineering Services Private Limited was hired for assisting the Engineer in Construction Supervision. This interim arrangement shall continue till a regular Supervision Consultant is hired through Bank Procurement process.
Theme Engineering Services Pvt. Ltd. has commenced its services with effect from 1st Nov, 2010. The Expenditure for this interim arrangement shall be borne by the Government of Odisha.
Items |
Provisions |
Upto Feb-2011 |
Upto Mar -2011 |
Financial Progress (Rs. Cr.) |
216.23 |
21.58 |
24.32 |
Physical Progress |
|||
Road |
95 Km |
BC:7.12 km |
BC:7.12 km |
Tree Cutting : |
7299 |
3645 |
3645 |
Land Acquisition |
79 villages |
74 village |
74 villages |
R&R |
30.6 Km |
PAPs Asper RAP –158 Nos (1st MS) |
PAPs Asper RAP –158 Nos (1st MS) |
Utility Shifting : |
|
|
|
Pipeline shifting |
17,220 mtr |
4000 mtr completed |
4200 mtr completed |
Tube Wells |
88 nos |
46 no.s |
46 nos |
Electric Lines |
SH 53: 39.5 km |
55 kmcompleted |
55 kmcompleted |
Bottleneck :
Agency: : |
M/s BACKBONE – ARSS JV Plot No. 38, Sector – A, Zone - D Mancheswar Industrial Estate, Bhubaneswar – 751 010 |
Estimated Cost : |
Rs. 75,33,96,605 |
Contract Amount : |
Rs. 81,97,23,707 |
Date of Commencement : |
22.11.2008 |
Date of Completion Due : |
21-11-2010 |
Length Handed over to the Contractor : |
4.0 Km on November, 2009
|
1st Mile Stone : |
18.580 Km on dated 07.05.2010 |
Length Handed over to the Contractor : |
5 km on November, 2009 |
MILE STONES as per Contract. |
|
1st Milestone - Km.2/0 to Km.15/0 of SH-17 : |
8 Months from the date of commencement of works i.e. till 21st July, 2009 |
2nd Milestone - Km.15/0 to Km.30/0 of SH-17 : |
16 Months from the date of commencement of works i.e. till 21st March, 2010 |
Completion of the whole work : |
24 Months from the date of commencement of works i.e. till 21st Nov, 2010 |
Revised Mile Stones proposed as per EOT |
|
1st Milestone Km.5/0 - 18/0, 37/0 – 41/0 : |
13 Kms
|
2nd Milestone Km. 0/0 - 3/0, 18/0 – 23/0 |
15 Kms |
Completion of the whole work : |
13.0 Km |
TOTAL : |
41.0 Km. |
One independent Executive Engineer of OWD has been designated as “Resident Engineer” for this package to administer the Contract as “Engineer”. Theme Engineering Services Private Limited was hired for assisting the Engineer in Construction Supervision. This interim arrangement shall continue till a regular Supervision Consultant is hired through Bank Procurement process.
[ Theme Engineering Services Pvt. Ltd., Jaipur ]
Theme Engineering Services Pvt. Ltd. has commenced its services with effect from 1st Nov, 2010. The Expenditure for this interim arrangement shall be borne by the Government of Odisha.
|
Provisions |
Upto Feb-2011 |
Upto Mar- 2011 |
Financial Progress (Rs. Cr.) |
81.97 |
8.59 |
9.50 |
Physical Progress |
|||
Road (km) |
41 |
BC:0 km |
BC:0 km |
Tree Cutting : |
1348 |
644 |
645 |
Land Acquisition: |
31 villages |
28 village |
28 village |
R & R |
11.7 Km |
PAPs Asper RAP –338 Nos (1st MS) |
PAPs Asper RAP –338 Nos (1st MS) |
Utility Shifting : |
|
|
|
Pipeline shifting |
21,040 mtr |
10,210 mtr completed |
10,210 mtr completed |
Tube Wells |
46 nos |
42 no.s |
42 no.s |
Electric Lines |
41 Km |
26 kmcompleted |
26 kmcompleted |
Bottleneck :
Name of the Project corridor with Stretch |
Name of the District | Total nos villages of each corridor with 4(1) noti. For 6(1) purpose |
Total nos of proposals received by the PMU and estimate sanctioned by CE(WB) and sent to Revenue & Disaster Management Deptt. |
Total amount sanctioned in Rs.and paid to LAOs for 6(1) notification with the number of villages. |
Total nos of villages notified under Section 6(1) by Govt in Revenue Deptt. as per available records. |
Govt. in Revenue & Disaster Management Deptt's direction to the Collectors & District Magistrate to go ahead with the Acquisition of Land under Section-7. | Pocession handed over to Works Dept. | Total Area Acquired (in Acres) | |
Area of Notification | |||||||||
Bhawanipatna-Khariar Road, SH-16 - 68kms |
Kalahandi | 19 | 19 | Rs 5893160.00 19 Villages |
19/ 32.42 |
19 Nos of Villages | 19 no. of villages handed over | ||
Bolangir | 13+1 | 13 | Rs. 5154541.00 13 Villages |
13/ 28.50 |
13 No. Of village | 12 villeges handedover | 1-New | ||
Nuapada | 9 | 9 | Rs. 61,53,772.00 9 Villages |
9/ 8.65 |
9 no of villages | 9 villageshandover | |||
(A) Bhadrak-Chandbali Road, SH-9(45Kms) |
Bhadrak | 48+2 | 48 | Rs. 40306640.00 48 Villages |
48/ 29.13 |
48 nos. of villages | 48 vill. possession handed over(5-protest) | ||
(B) Bhadark-Anandpur Road, SH-53(50 kms) |
Bhadrak | 18 | 18 | Rs.23659856.00 18 villages |
18/ 20.29 |
18 nos. Of villages | 17 nos handedover |
||
Keonjhar | 11+3 | 11 | Rs19536351.00 11 Villages |
11/ 9.755 |
11 nos. Of villages | 10nos handedover |
|||
Berhampur- Taptapani- SH-17 -41 Kms |
Ganjam | 31 | 29 | Rs. 38095299.00 28 Villages |
28/ 55.138 |
29 nos. of villages | 28 villages handedover | Digapahandi revised valuation submitted to Govt. for approval. | |
TOTAL | 155 | 147 | Rs.135172670.00 146 villages |
146/ 183.883 |
147 nos. of Villages | 143 |
me of the Project Corridor with Stretch |
Name of the District | Total nos village | Total nos village(proposal) to be sent for 4(1) Notification | Total nos village proposals Recevied by the Revenue & DM Department | Total nos of villages notified by Govt in Revenue Department 4(1) | Total nos village proposals Recevied by the Revenue & DM Department U/S 6(1) | Total amount (Rs. Deposited) |
Total nos of village notified under Section 6(1) by Govt. in Revenue Deptt. | Total nos of village submited for 7-order to Govt |
Total No. of village Notified by Gov. U/s 7 |
|
Jagatpur-Chandbali Road, (SH-09A & SH-09)106 kms. |
Kendrapada | 62 | 53 | 53 | 53 | 51 | 154027652.00 | 50 | 48 | 17 | |
Cuttack | K. Para Divn | 6 | 6 | 6 | 6 | 6 | 4 | 2 | 2 | ||
CTC Divn | 38 | 35 | 35 | 35 | 34 | 26 | 23 | 13 |
|||
Total | 44 | 41 | 41 | 41 | 41 | 140691585.00 | 30 | 25 | 15 | ||
Bhadrak | 7 | 6 | 6 | 6 | 5 | 1734666.00 | 5 | ||||
Total | 114 | 100 | 100 | 100 | 95 | 296453903.00 | 85 | 73 | 32 |
Sl. | Name of the Package | No. of Total PAPs as per DPR | No. of PAPs in 1st Milestone | Identification & Verification | R&R Entitlement with structure valuation | Opening of Joint Bank Account (PAP & E.E) | |
RAP | NonRAP | ||||||
1 |
PO-1 (Bhawanipatna-Khariar Road, SH-16) |
1096 |
103 | 21 | 124 |
120 |
120 |
2 |
PO-2 (Chandabali Bhadrak Anandapur Road SH-9 & SH-53) |
3889 |
153 | 119 | 260 |
260 |
260 |
3 | PO-3 (Berhampur-Taptapani Road, SH-17) | 1361 | 76 | 42 | 118 | 114 | 114 |
Total |
|
|
332 | 182 | 502 |
494 |
494 |
Please Refer Monthly Progress Report
Odisha State Roads Project has requested to Odisha State Aids Cell(OSAC)s for technical support and sensitisation of NGOs,Contractors,Consultants and Project Mangers dealing with the Project road corridors.The process of sensitisation, by fixing and displaying Posters and Organising road shows and campaigns, is under process at plant sites and in vulnerable areas in each road corridor.
As per Clause 20.2 of Volume:lI (Particular Conditions & General Conditions) of Civil Work Contracts Dispute Resolution Board (DRB) has been constituted.
As per agreement the Dispute Board visited all Year-1 Road packages under Orisaa State Roads Project .The proceedings of DRB meeting are as follows.