EIC-Cum Secretary to Govt., Works Department reviewed the status of electrical utility shifting in the 3 year-1 road corridors of OSRP on 13.07.2011. The goals/target dates were fixed in consultation with Superintending Engineer, Electrical (R&B) Circle , Nirman Soudha, BBSR. Executive Engineer, GED & Executive Engineer -II,PMU to complete the said assignments in all the three year-1 road corridors by 15.08.2011 in order to obtain utility free corridors and desired work front for the contractor to expedite the road construction in all the three packages.